Change Management Procedure

How changes to services and configuration items are requested, assessed, approved, scheduled, implemented and reviewed, including standard and emergency changes.

SXL-SM14Procedure3,180 words 14 min readOwner: Change manager
Sign in to download the PDFFree. You return straight to this document after you sign in.
Template draft. Replace everything in [square brackets] with your own decision, delete what does not describe what you really do, and approve it through your own document control. It is not legal advice and does not make an organisation compliant or certified.

1. Introduction

Most serious service failures follow a change that nobody assessed, tested or told others about. At the same time, an organisation that cannot change quickly cannot respond to customers or threats. This procedure lets the Organisation change services at the pace the business needs while keeping the risk visible, the decisions accountable and the records complete.

The security aspects of change, such as review of security impact and separation of environments, are set out in the Change Management Policy and Procedure; this procedure covers the service management process.

2. Purpose

The purpose is to make sure that every change to a service or a configuration item is requested, assessed for benefit and risk, authorised at the right level, scheduled to avoid conflict, implemented with a way back, and reviewed, so that changes succeed without causing incidents.

3. Objectives

  • Every change to a production service is recorded before implementation, apart from standard changes that are logged as they are done.
  • At least [95%] of changes are successful, meaning they achieve their purpose with no incident or unplanned outage.
  • Emergency changes remain below [5%] of all changes, and each is reviewed afterwards.
  • Changes are approved by an authority proportionate to their risk, and no person approves their own change.
  • Conflicts between changes are found and removed before the change window through a single change calendar.
  • The CMDB and service documentation are updated within [2 working days] of each change closure.

4. Scope

  • In scope: addition, modification, removal or replacement of services, service components, configuration items, service level targets, supplier arrangements, documents that define services, and the security configuration of any of them.
  • In scope: changes initiated by service owners, projects, resolver groups, suppliers, security, customers and the problem process.
  • In scope: emergency changes made to restore service or to stop an active security threat.
  • Out of scope: service requests that follow a fixed procedure with no effect on the service (for example a password reset), which are handled by the service request process, and changes to staff or organisation structure.
  • Applies to: all staff and suppliers who plan, assess, approve or make changes in the production environment.

5. Terms and definitions

TermMeaning
ChangeThe addition, modification or removal of anything that could have an effect on services.
Request for change (RFC)A formal proposal for a change, recorded in the ticketing tool.
Change authorityThe person or group that approves a change. It may be the change manager, a change advisory board, or senior management, depending on risk.
Change advisory board (CAB)A group that advises the change authority and reviews higher-risk changes; it includes technical, service and security members.
Standard changeA pre-approved, low-risk, repeatable change that follows a documented procedure.
Normal changeAny change that is not standard or emergency, assessed and approved case by case.
Emergency changeA change that must be made faster than the normal process allows, to restore a service or stop a threat.
Change calendarThe schedule of approved changes and blackout periods.
Post-implementation reviewA check after a change that it achieved its purpose and caused no harm.

6. Change Management Policy

6.1 Objectives of the policy

  • Protect the services customers depend on from harm caused by change.
  • Enable the changes that the business needs to be delivered quickly and predictably.
  • Give every change an accountable owner, a record and a decision that can be explained later.
  • Learn from failed changes and feed what is learned into design, testing and the next change.

6.2 Principles

  • Every change is recorded, and a change that is not recorded is a breach of this policy and is treated as an unauthorised change.
  • The effort of control matches the risk: low-risk repetitive changes are pre-approved, high-risk changes are examined by senior people.
  • No one approves a change they requested or will implement, apart from pre-approved standard changes.
  • Every change is tested or otherwise verified in a place that resembles production before it is made, and has a backout plan that has been considered.
  • Changes are made in agreed windows and avoid blackout periods, unless the change authority accepts the risk in writing.
  • Customers and users are told in advance of changes that affect them.
  • Security and privacy impact is assessed for every change that is not standard, by information security where the risk is medium or higher.
  • Changes made by suppliers on the Organisation's behalf follow this procedure.
  • Emergency change is for emergencies, not for late planning, and is reviewed within [2 working days].

6.3 Policy statements

  • Only the change manager, or a deputy appointed in writing, may approve normal changes of low risk; others follow the approval authority table.
  • Developers do not have write access to production unless it is granted for the duration of an approved change.
  • All change records identify the configuration items affected, so that the CMDB can be updated.
  • A change that fails is backed out unless the change authority decides otherwise, and a review is held.
  • Management receives a monthly report of volume, success rate, emergency changes and unauthorised changes.
  • Adherence to this policy is checked by internal audit and by the change manager's monthly sample.

7. Roles and Responsibilities

RoleResponsibilities
Process ownerOwns this procedure, appoints the change manager and approves the approval authority table and the standard change catalogue.
Change managerRuns the process, triages requests, chairs the CAB, keeps the change calendar, monitors success, and produces the monthly change report.
Change requesterDescribes the change, its reason and the benefit, and supplies the plans, tests and backout.
Change ownerIs accountable for one change from request to review. Usually the requester or a delegated engineer.
Change implementerCarries out the change as approved and records the result.
Change authorityApproves or rejects changes within its limits. Levels are given in the approval authority table.
Change advisory boardReviews medium and high risk changes for technical, service, security and customer impact, and advises the change authority.
Emergency change groupA small group of change manager, service owner and technical lead (or their deputies) that can approve emergency changes at any hour.
Service ownerConfirms business timing and impact and accepts residual risk to the service.
Information securityAssesses security and privacy impact, and may require extra controls or reject.
Release manager and configuration managerSchedule releases and keep the CMDB up to date for each change.
ActivityResponsibleAccountableConsultedInformed
Raise request for changeChange requesterChange ownerService ownerChange manager
Triage and categoriseChange managerProcess ownerChange ownerService desk
Assess risk and impactChange ownerChange managerInformation security, Service owner, Resolver groupsConfiguration manager
Approve changeChange authorityProcess ownerChange advisory board, Service ownerChange owner
Schedule and keep calendarChange managerProcess ownerRelease manager, Service ownerService desk, Customer representative
Implement and record resultChange implementerChange ownerResolver groupsService desk
Review and closeChange ownerChange managerService owner, Configuration managerProcess owner
Approve emergency changeEmergency change groupChange managerInformation securityTop management

8. Change Management Process

8.1 Inputs and outputs

InputsOutputs
Requests from service owners, projects, suppliers and customersApproved, rejected or deferred changes with reasons
Problem records and known errors needing a fixChange calendar and communication of schedule
Incident records requiring urgent changeImplemented changes with results and reviews
Release plans and service design packagesUpdated CMDB and documentation
Security alerts and vulnerability findingsMonthly change report and improvement actions
Risk assessments and lessons from earlier changesStandard change catalogue, kept current

8.2 Process flow

  1. The requester raises an RFC in the ticketing tool.
  2. The change manager checks completeness and decides the change type: standard, normal or emergency.
  3. Standard changes are executed under their procedure and logged. Normal and emergency changes continue to assessment.
  4. The change owner assesses risk and impact; the change manager assigns the risk level.
  5. The change authority for that level approves, rejects or defers the change.
  6. The change is placed in the change calendar and communicated.
  7. The implementer makes the change in its window and records the result; failure triggers the backout plan.
  8. The change owner verifies the result, updates the CMDB and documents, and closes the record.
  9. The change manager reviews selected changes after implementation and reports.

8.3 Types of change

TypeDescriptionApprovalLead time
StandardLow risk, well understood, repeatable, with a documented procedure and a place in the standard change catalogue. Examples: add a user to a group, replace a failed disk, renew a certificate.Pre-approved by the process owner when the entry is added to the catalogue; no case-by-case approval.Logged when done, or booked [1 working day] ahead where it affects users
NormalAny change that is not standard or emergency. Divided into low, medium and high risk by the risk matrix.By the change authority for the risk level in the approval authority table.Low [2 working days]; medium [5 working days]; high [10 working days]
EmergencyA change needed at once to restore a failed service, to stop a security incident or to meet a legal deadline.By the emergency change group, in person or by recorded message.As fast as safety allows; paperwork within [2 working days]
Note. A standard change is added to the catalogue only after the same change has been made successfully at least [3 times] under normal change, with documented steps and checks. The catalogue is reviewed every [6 months] and an entry is removed after a failure that was caused by the change itself.

8.4 Request for change

  1. RaiseThe requester raises an RFC with reason and benefit, services and CIs affected, proposed date and window, implementation steps, test evidence, backout plan, who will implement, and who needs to be told. Owner: requester. Target: lead time for the type.
  2. CheckThe change manager checks completeness and rejects or returns incomplete requests with comments. Target: [1 working day].
  3. CategoriseThe change manager sets the type, a first risk view and the change authority, and names the change owner. Target: [1 working day].
  4. LinkRelated incidents, problems, releases and projects are linked so that the history is complete.

A change that arises from an incident or problem keeps the link to that record, and the incident or problem is not closed until the change is closed.

8.5 Assessment of risk and impact

  1. Identify impactThe change owner lists the services, customers, suppliers and CIs affected, and the effect if the change fails. Use the CMDB dependencies.
  2. Rate likelihood and impactScore each from 1 to 3 using the matrix below. Consider previous failures, complexity, test quality, timing and the skill of the implementer.
  3. Assess security and privacyInformation security rates security and privacy effect for every normal change of medium or higher risk and any change touching customer data, access control, network boundary or cryptography.
  4. Check capacity and continuityThe change owner asks the capacity manager and continuity manager for comment where load or recovery is affected.
  5. Confirm the backoutThe backout plan states the trigger, steps, time to execute and who decides. It is tested where the risk is medium or higher.
  6. RecordThe assessment is stored on the RFC. Target: complete [2 working days] before the CAB.
Impact of failure / LikelihoodLow (1)Medium (2)High (3)
Minor, one team affected (1)LowLowMedium
Moderate, one service degraded (2)LowMediumHigh
Major, a tier 1 service or many customers (3)MediumHighHigh

8.6 Approval authority

A change is approved by the level that matches its risk. The approval is recorded in the RFC with the name, time and any conditions. The requester and the implementer cannot approve their own change.

Risk levelChange authorityAdvice sought fromTime to decide
StandardPre-approved by the process ownerNot applicableNot applicable
LowChange manager or deputyService owner for timing[2 working days]
MediumChange advisory board with the service ownerInformation security, resolver groups, capacity managerAt the next CAB, within [5 working days]
HighChange advisory board and the process owner, with top management informedAs medium, plus customer representativeWithin [10 working days]
Major (new service, large migration)Handled under the Service Design and Transition Procedure; gate 5 approval by the change authorityTransition teamAs the transition plan states
EmergencyEmergency change groupInformation security by phoneWithin [1 hour] of the request, any time

The change advisory board meets [weekly] and on demand. Quorum is the change manager, a service owner or delegate, one resolver group lead and information security. Its agenda covers: review of changes since last meeting (successes, failures, emergency changes), changes proposed for approval, the change calendar for the next [2 weeks], and lessons and improvements.

8.7 Scheduling and the change calendar

  • The change manager keeps a single change calendar covering all services, showing approved changes, owners, windows, affected services and blackout periods.
  • Standard windows are [Tuesday and Thursday, 22:00 to 02:00 local time] for tier 1 services; other windows are agreed with the service owner.
  • Blackout periods apply for [month-end close, customer peak events and the last week of the financial year], and changes then need approval from the process owner.
  • Two changes affecting the same service or the same CI are not placed in one window without a stated reason.
  • The calendar is published to the service desk, resolver groups and customer representatives, and updated within [1 working day] of any move.
  • Where several changes belong together, the release manager groups them into a release under the Release and Deployment Management Procedure.

8.8 Implementation

  1. Confirm readinessBefore the window the change owner confirms approval, tests passed, resources ready, backups taken and communications sent. If any is missing, the change is postponed.
  2. StartThe implementer informs the service desk and the monitoring team that the change is starting and sets a monitoring note on the affected services.
  3. ImplementMake the change exactly as approved. Any deviation is recorded and, if it alters the risk, referred to the change authority.
  4. VerifyThe implementer runs the post-change checks in the plan and the service owner or monitoring confirms service health. Target: within [30 minutes] of finishing.
  5. Back out if neededIf the checks fail or the window ends, the change owner invokes the backout plan, informs the change manager, and records the reason.
  6. RecordThe implementer records start and end time, result (successful, successful with issues, backed out, failed), and actual effects. Target: same working day.
ResultMeaningAction
SuccessfulPurpose achieved; no incidentClose after review
Successful with issuesPurpose achieved; minor incident or deviationReview and learn; close
Backed outChange reversed as plannedUnderstand cause; raise a new RFC
FailedPurpose not achieved, service harmedRaise incident; mandatory review

8.9 Emergency change

  1. DeclareThe incident manager, service owner or security lead requests an emergency change by phone and raises the RFC as soon as possible. Owner: requester.
  2. ConveneThe change manager (or deputy) convenes the emergency change group within [1 hour]. A group of at least three members including one service owner approves.
  3. Assess brieflyThe group considers what will happen if the change is not made, what could go wrong, and how to reverse it.
  4. Decide and recordDecision, names and time are recorded. Security impact is checked by phone.
  5. ImplementCarry out the change under the same implementation rules, with a person to check results.
  6. Complete recordsFull details of the RFC and CMDB updates are completed within [2 working days], and a review is held within [5 working days].
Note. If three emergency changes are made for the same cause in a quarter, the change manager raises a problem record and reports it to management.

8.10 Post-implementation review and closure

  1. Review sampleThe change manager reviews every failed, backed out and emergency change, every change with incidents, and a sample of [10%] of the others. Target: [5 working days] after implementation.
  2. QuestionsWas the purpose achieved? Was the plan followed? Were there incidents? Was the backout needed? Were the estimates of risk and time correct? Was the CMDB updated?
  3. LearnFindings are recorded; weaknesses in tests, assessment or planning go to the improvement log. A repeat failure leads to a problem record.
  4. CloseThe change is closed only when the CMDB and documents are updated and review items are done.

9. Interfaces with other processes

ProcessInterface
Incident and problem managementIncidents may need emergency change; problems produce changes; failures create incidents.
Release and deployment managementReleases are authorised by change records and built from approved changes.
Configuration and asset managementChanges name the CIs and trigger CMDB updates.
Service design and transitionMajor changes are managed as transitions with gate 5 approval through change management.
Capacity and demand managementCapacity changes follow this procedure; capacity advises on risk.
Supplier managementChanges at suppliers that affect services are submitted as RFCs.
Information security management for servicesSecurity impact is assessed for changes; security fixes may be urgent changes.

10. Key Performance Indicators

MeasureTargetSourceFrequency
Change success rate[95%] or higherChange recordsMonthly
Emergency changes as a share of all changesBelow [5%]Change recordsMonthly
Unauthorised changes found[0]; each one investigated within [5 working days]Change and configuration auditMonthly
Incidents caused by changeBelow [5%] of all incidentsIncident recordsMonthly
Changes implemented within their approved window[95%]Change recordsMonthly
Changes closed with CMDB updated within [2 working days][95%]CMDB audit sampleMonthly
Reviews held for failed, backed-out and emergency changes[100%]Review recordsMonthly
RFCs returned as incompleteBelow [10%]Change recordsQuarterly

11. Records and evidence

RecordKept inOwnerRetention
Request for change with assessment, approval and resultTicketing toolChange manager[3 years]
CAB agenda and minutesDocument management systemChange manager[3 years]
Emergency change decisions and reviewsTicketing toolChange manager[3 years]
Change calendar and blackout listTicketing tool or calendarChange manager[1 year]
Standard change catalogue and its historyDocument management systemProcess ownerLife of the entry plus [3 years]
Monthly change reportDocument management systemChange manager[3 years]

Annexure A: Change request form

FieldEntry
RFC number and date raised
Requester and change owner
Title and description of the change
Reason and expected benefit
Type (standard, normal, emergency)
Services and configuration items affected
Proposed date, window and duration
Implementation steps and implementer
Test evidence
Backout plan, trigger and time to execute
Risk: likelihood, impact, level
Security and privacy assessment
Communication plan
Approval: name, role, decision, date, conditions
Result and date implemented
Review notes and CMDB updated (yes, no)

Annexure B: Change calendar

Date and windowRFC numberChange titleServices affectedType and riskOwnerStatus
[date, 22:00 to 02:00][CHG-0001][Database version upgrade][Customer platform][Normal, medium][Name][Approved]
[date range]Blackout[Month-end close][All finance services]Not applicable[Change manager][Published]

Annexure C: Standard change catalogue entry

FieldEntry
Name and reference[Add user to a group, STD-001]
Trigger and who may request
Systems and CIs affected
Procedure steps
Checks after the change
Risk rating and reasons
Approved by and date
Review date

Annexure: Document history

VersionDateAuthorReviewed byApproved bySummary of change
[1.0][date of issue][Process manager][Process owner][Management representative]Initial issue of SM14

12. Exception

Exceptions to this document are allowed only where compliance is not practicable and the risk has been assessed. A request must state what is to be excepted, why, the risk it creates, the compensating controls, and an end date no later than [6 months]. It is approved in writing by the document owner and the risk owner, recorded in the exceptions register, and reviewed at the end date. An exception does not change the document.

13. Enforcement

Compliance is monitored through internal audits, management review and routine checks by the document owner. Non-compliance is reported through the incident or non-conformity process and handled under the organisation's disciplinary procedure, and under the terms of any contract for people who are not employees. Serious or repeated non-compliance may lead to loss of access and, where the law is broken, to referral to the authorities.

14. Review

This document is reviewed at least every [12 months], and when there is a significant change to the organisation, its systems, its risks or the law, or after an incident that shows it was not effective. Each review is recorded in the revision history.

ISO/IEC 20000-1:2018 references

ReferenceTitle
8.5.1Change management
8.2.6Configuration management
8.1Operational planning and control
8.5.3Release and deployment management